The project to renovate the wastewater treatment system at An Phu Plaza, carried out by NTS Engineering Co., Ltd, aims to upgrade the efficiency of domestic wastewater treatment and ensure the effluent quality meets current QCVN standards.

Through the survey and analysis of the current condition, NTS found that the system had shown signs of serious deterioration, with the actual treatment capacity reaching about 70% of the original design. This not only poses a risk of environmental pollution but also affects the operational efficiency and reputation of the building.

NTS is a consulting, design, and renovation unit that has proposed and implemented optimal technological solutions, ensuring that the system operates stably and safely after renovation, with the quality of the effluent meeting high standards.

 

Challenge

Renovating a wastewater treatment system in a continuously operating building requires:

  • Flexible and precise solutions
  • The treatment system is located in the basement, with limited space, low ceilings, and interspersed with many other engineering items. Therefore, the renovation plan must be carefully, and suitable for the actual conditions of the project
  • Other building operations must continue to operate. This requires careful planning of the renovation process so as not to affect other building operations
  • In addition, there are requirements for odor and noise control during implementation

Solution

The wastewater treatment system at An Phu Plaza applies AO technology combined with MBBR. NTS is required to improve the treatment efficiency without expanding the existing tank. The proposed renovation solutions include:

  • Clean old wastewater treatment system
  • Add suitable chemicals
  • Add microorganisms in a reasonable ratio
  • Apply deodorizing measures to the system
  • Build soundproofing systems to meet project requirements

Analysis

Assessment of water quality and condition

Design

Plan and design appropriate systems

Deployment

Installation and operation of water treatment systems

Monitor

Regular system monitoring and maintenance

Results

After renovation, the system operates stably, and the output water quality meets QCVN standards.

Summary table of some typical output wastewater quality parameters after testing and renovation:

Items Value Unit

Capacit

120

m3/day.night

BOD Removal Efficiency

< 40

mg/L

COD Removal Efficiency

< 70

mg/L

Total Coliform

< 3000

MPN/100ml

35%
Increase treatment efficiency
40%
Reduce periodic maintenance costs

Project information

Location:
117-119 Ly Chi Thang, Ward 7, District 3, HCMC
Year:
2015
Technology:
AO+ MBBR technology

Project data

120
m³/day.night
Capacit
7-10
Days
Implementation time
20
years
System lifespan
0.2
kg BOD/kg MLSS/day
F/M